Our Solution
The overall project for a new high school and athletic complex included a new high school building, stadium, multipurpose building, Ag/Vo-tech building, greenhouse, tennis courts, ball field areas, curbed guttered driveways and parking areas, handicap accessible sidewalks, driveways, drainage structures and detention facilities for approximately $43,860,000.
Hayter Engineering services included consultation with the City of Paris, the Texas Department of Transportation, as well as coordination with the architect and Paris ISD. Services provided by Hayter Engineering are listed to the right.
Hayter Engineering coordinated with TxDOT and the City of Paris to improve the intersections of Loop 286, Collegiate Drive and Jefferson Road to accommodate the new high school traffic.
LOCATION
Paris, Texas
CONSTRUCTION COST
$4,377,000
(FOR HAYTER ENGINEERING DESIGNED FACILITIES)
SERVICES PROVIDED
- Off-site Water & Wastewater Design
- Water & Wastewater Design
- Paving & Sidewalk Design including handicapped accessibility
- Site Grading Design
- Storm Drain & Detention Ponds Design
- Construction Review
- Warranty Review