Our Solution
Hayter Engineering prepared the application for Bonham to apply to the Texas Water Development Board for a low interest loan from the Drinking Water State Revolving Fund for a new 500,000 gallon elevated tank to improve fire protection and improve the water service to their customers. The demolition of an existing 400,000 gallon elevated tank was performed after the new elevated tank was put into service.
The new 6 column Toro-Ellipsoidal welded steel elevated tank was erected in place with foundation and piping, interior and exterior painting, electrical, site work, fencing, landscaping, and SCADA system and controls.
This project was part of a larger $7,355,000 project, which also included: coating and repair of the DeRose elevated tank and two ground storage tanks; a new high service booster pump station facility; two contracts for water distribution mains; material procurement for repair of streets cut for water line installations; water meters procurement; water meter installation & Fixed-Read AMI System; and coating/repair of the Silo Road ground storage tank and Silo Road elevated tank.
LOCATION
Bonham, Texas
CONSTRUCTION COST
$923,101
SERVICES PROVIDED
Application for Finance
Engineering Feasibility Report
Design Surveying
Geotechnical Engineering
Structural Engineering
Civil Engineering
Design Plans & Specifications
Construction Bid & Award
Grade Staking
On-Site Observation
Construction Review
Record Drawings
Warranty Review